Friday, March 6, 2009
Cross Raising Parking Instructions
Come join us for the historic raising of the cross at the NBCF Worship and Family life center at 10:00 AM. There is no parking on site, so download this page at http://thenbcf.org/The Raising of the Cross.pdf for directions on where to park and what to wear for this important day.
Sunday, March 1, 2009
Mar 1 09 Congregational Update
Congregational Update
Mar 1 09 Congregational Update
View more presentations from dankcorn.
Friday, February 27, 2009
Raising The Cross
Join us on Saturday, March 7th at 10:00 AM when the Cross will be raised to the top our Worship and Family Life Center.NBCF Worship & Family Life Center
19300 108th Avenue SE
Renton, WA 98058
Following the Cross raising, you will be able to view the progress to date inside the building and learn of new ministry opportunities available at the new site.
Please dress for the weather. Parking is limited so plan to car-pool or ride one of the NBCF Shuttle Busses from the Lindbergh High School Parking Lot or from one of our satellite parking areas.
Wednesday, February 11, 2009
Roof Finished, Installing the Well For the Cross
The roof has been completed, with final preparations for the mechanical well that will hold the Heating and Airconditioning Units and the Cross. Framing for the north side classrooms is finishing as well.
Friday, January 23, 2009
Roof goes on, supports finishing underneath.
The roof is going on, with the good weather allowing the roofers to cover ground quickly. The west side is nearly finished, and the east side will go on next week, weather permitting. The last structural beams are going up inside, preparing for the space that will hold the cross to be installed late next month. Keep checking back to see how this project continues to move forward.
Tuesday, January 13, 2009
Sunday, December 7, 2008
In the month of November, steel work continued and foundation work has nearly finished. Rough electrical and plumbing work continue and HVAC has begun. Framing of interior walls have begun by Unlimited Construction. A new roof started as well, right in the middle of the storms at the beginning of the month. Everyone is working together with over 4500 hours of work completed and no accidents. Praise to God.